The end of an era, Wilmington’s Kerr Avenue construction almost complete (supposedly)

The project originally began in 2016 and was slated for a 2018 completion date but a number of setbacks have pushed that completion date until fall 2019

An asphalt drum roller parked at northwest corner of Kerr Avenue and Market Street on Monday. (Port City Daily photo/Mark Darrough)
An asphalt drum roller parked at northwest corner of Kerr Avenue and Market Street on Monday. (Port City Daily photo/Mark Darrough)

WILMINGTON — There are people that have lived in Wilmington for years and have never seen Kerr Avenue without construction, barrels, and detours — but all that could soon change, as long as things go according to plan.

Construction on Kerr Avenue is coming to an end as crews begin the final paving of the road next week.

According to NCDOT spokeswoman Lauren Haviland, “The final layer of paving on Kerr Ave. will begin early next week. It’s expected to take four weeks, but it’s weather dependent. The work will be done at night.”

The $22 million project to widen the corridor began in 2016 and was originally planned for completion back in 2018 — but several delays and setbacks pushed that timeline until March of 2019. Obviously, that never happened, but the NCDOT and crews have been working on the road steadily.

One of the biggest problems the crews ran into was the exceptionally wet year Wilmington saw last year with more than 100 inches of rain falling.

“We’ve had an unusually wet year,” Engineer and project lead Jason Rivenbark said in a previous interview with Port City Daily. “We cannot pour concrete when it’s raining … Plus, there’s underground utilities we’ve encountered that we did not expect to run into.”

Once paving is complete, the final pavement marking will be installed and the total completion date is now set for early fall, Haviland said.

According to NCDOT, “the project includes widening to four lanes North and South Kerr Avenue between Martin Luther King Jr. Parkway (U.S. 74) and Randall Parkway. Bicycle lanes and sidewalks and a landscaped median will also be added to the road. Improvements at Market Street include concrete medians and a quadrant left intersection, which reduces congestion and travel time by prohibiting left turns at main intersections. The median and the intersection will improve safety and capacity at this busy city intersection.”