Intersection of Walnut and Front closed until mid-April

WILMINGTON — The intersection of Front and Walnut streets outside Cape Fear Community College’s McLeod Building downtown will remain closed into mid-April to accommodate improvements to the area’s drainage system.

The intersection of Front and Walnut streets Friday afternoon. At rear right is CFCC’s Union Station. Out of frame to the left is the school’s McLeod Building. Photo by Ben Brown.

The site was off-limits to traffic Friday afternoon, the intersection’s ground-up asphalt surrounded by orange-striped barricades and heavy equipment.

Businesses were open as usual, as was the school.

City spokesman Dylan Lee said Friday the closure will remain in place for the duration of the project, to wrap in the spring.

“This project will replace underground drainage systems and protect Front Street from cave-ins that can occur during heavy rains,” a bulletin from the city explained.

Along with another downtown stormwater fix, at Water and Ann streets next to Chandler’s Wharf, the work “is intentionally occurring during the least busy time of year for downtown merchants,” a release from the city explained earlier this month. “The city is reaching out to affected merchants in a number of ways to keep them informed.”

City employees, not contractors, are performing the improvements, funded through the city’s operating budget.

The entire stormwater maintenance budget for fiscal 2012-2013 is $3.4 million, covering maintenance of Wilmington’s public drainage system, including open drainage components like ditches and ponds and closed systems like those now under construction.