CAROLINA BEACH — As a part of an agreement with Carolina Beach, Civil Works Contracting, the company hired to perform the dredging of the lake in Carolina Beach, has begun demobilization of its equipment — which has raised some questions of why equipment is being used. As it turns out, in order to demobilize the company must also break down the barges that are being used so as to not accrue more rental fees, this means putting some of the material on the barges back into the lake.
“As part of the demobilization the contractors are allow to remove the equipment from the lake area. In order to remove the barges the contractor would need to remove the soil from the barges, dismantle them and move them out of the lake. This is an approved activity,” Town Manager Michael Cramer said.
Work has been suspended after the U.S. Government told the town to stop placing the dredging spoils on its property at Military Ocean Terminal at Sunny Point.