
WILMINGTON — Drivers may see an early end to the lengthy detour currently taking them around Greenfield Lake, instead of taking Third Street onto Carolina Beach Road.
Announced in April, North Carolina Department of Transportation repairs to a 1940s culvert under Third Street were expected to shut down the intersection through the end of the year. But according to NCDOT spokesman Brian Rick, the project is now on track to be completed in early December.
According to Rick, construction of a new culvert has been completed, and construction crews are now rebuilding the multi-street intersection where Front Street and Third Street meet and become Carolina Beach Road.
Since April, southbound motorists have been directed via signs to Dawson Street, 16th Street, Shipyard Boulevard and Carolina Beach Road. Drivers heading northbound on 3rd Street will take Carolina Beach Road to Shipyard Boulevard and 17th Street to Wooster Street. The six-mile detour takes 15 minutes under ideal circumstances, considerably more during peak traffic times.

