Paving is progressing along North Third Street in Wilmington, where 3 inches’ worth of new asphalt is being laid northward from Market Street to the Martin Luther King Jr. Parkway.
Traffic continues to be routed via single lanes in each direction on the typically four-lane road, which is undergoing a $10.4-million enhancement of water and sewer lines, underground utilities, sidewalks and curbing, and landscaping amenities.
Work started a year ago and has entered its final phase, with paving working its way up from Market to the parkway. Milling of existing asphalt started in October, and a new layer of asphalt—the first the road has received in more than a decade—is being added in a northward progression on up to the parkway.
Intermittent closures of side streets will continue through mid-December, with the total project scheduled for completion by year’s end. Paving south of Campbell Street is slated for completion by mid-November, according to a city overview of the project.
More information about the project can be found on the City of Wilmington’s website.